Himalayan Energy – Hydro Power In Nepal

Financial Highlight

Enhancing Nepal’s energy security by helping to utilize its renewable
hydro resources and reduce imports of electricity

Financial Highlights

Enhancing Nepal’s energy security by helping to utilize its renewable
hydro resources and reduce imports of electricity

Total Project Cost NPR 595.2 Million

  • Loan: NPR 416.6 Million (70%)
  • Equity: NPR 178.6 Million (30%)

Cost per MW: NPR 19.84 Million

Projected Revenue (Year 1): NPR 99.9 Million

Payback Period: 6.89 years (simple); 11.49 years (discounted)

Return on Equity (ROE): 18.06%

Debt Service Coverage Ratio (DSCR): 1.47x

Graph representation

Revenue Projection

NPR 10.6 Cr. Annually

KEY Technical Features

Energize Society With Sustainable
And Reliable Energy Systems!

Gross Head: 322.2 m

Net Head: 314.6 m

Turbine Type

European-manufactured Pelton
turbines (2 × 1.563 MW)

Transmission Line

33 kV, 13 km

Construction Period

18 months

Power House

Surface design (21 m × 17.5 m × 11 m)

PPA Status

Draft Unavailable